Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

8 revisions
Phil at Aug 24, 2023 09:43 AM

250

Special Meeting
April 9, 1959

Bids Itemized

installation of the new steam boiler presently to be installed. The following bids were received:

Bidders Amount

Newberg and Bookstrom $24,166.00
Ray Martin Company 25,525.00
Natkin & Company 29,495.00

It was moved by Regent Elliott, seconded by Regent Greenberg, motion put to vote and carried, directing the low bid from Newberg and Bookstrom in the amount of $24,166.00 for the necessary work to be performed in the rearrangement of the city campus power plant space and installation of a new steam boiler be accepted. Mr. Donaldson is hereby authorized to negotiate contracts with Newberg & Bookstrom for this work.

Resolution providing retirement pay for certain Agr.Extension personnel for stated period of time

RESOLUTION

WHEREAS, the following named persons were employees ot The Board of Regents of the University of Nebraska in the Agricultural Extension Service for many years, retiring therefrom on the dates set opposite their respective names:

W. R. Brokaw December 31, 1947
Jessie Green April 30, 1949